Requests for Equitable Adjustment: Notice and Documentation Basics for Subcontractors
Review change authority, notice, documentation, pass-through, and pricing requirements before extra work becomes a disputed cost.
Extra work often begins before the parties agree on price. A field direction, revised interpretation, access problem, schedule impact, differing condition, or Government-caused change can increase cost while the subcontractor is still expected to perform.
For a federal subcontractor, recovery usually depends first on the subcontract: who can direct a change, when written notice is due, what records must be kept, whether the prime will sponsor an upstream request, and how settlement or payment is handled.
REA vs. Formal Claim
A request for equitable adjustment can seek a change to price, schedule, or other contract terms after changed performance. A formal claim under the federal disputes framework has a different procedural posture and can require certification when the amount exceeds the applicable threshold.
For a detailed comparison, see REA vs. Claim for Federal Subcontractors.
Build the Record Around Three Questions
- Entitlement: What contract term, direction, condition, delay, or change supports the requested adjustment?
- Causation: How did that event affect specific labor, material, equipment, schedule, productivity, or other performance?
- Quantum: What contemporaneous records support the amount of the requested price or time adjustment?
Notice Comes Before the Perfect Pricing Package
Subcontracts can impose short written-notice periods for changes, delays, or differing conditions. A subcontractor should not delay the initial notice while waiting for every cost impact to be known. Follow the actual subcontract procedure and supplement the record as facts develop.
Practical Administration Steps
- Identify the people authorized to direct changed work.
- Send written notice to the contractually required recipient when a potential change occurs.
- Separate changed-work cost from base-scope cost as early as possible.
- Preserve schedule updates, daily reports, invoices, correspondence, and field records.
- Review pass-through and sponsorship provisions before assuming the prime will present the matter to the Government.
- Read modification and payment releases before signing away unresolved adjustment rights.